Revisions to
Chapter 62-610, F.A.C.
11/19/07
The rule revisions that went into effect on November 17, 2007,
included the following:
- Deletion of Rule 62-610.800(10)(a)4, F.A.C. This rule is
inconsistent with the directive in 403.064(8), F.S.
- Encouragement of metering of reclaimed water in accordance with
recent statutory directives in Sections 403.064(16), and
373.1961(4)(a), F.S., and Rule 62-40.416(3), F.A.C.
- Revision of Rule 62-610.451, F.A.C., regarding minimum system
size.
- Deletion of outdated references to Rules 62-550.405, 410, and
415, F.A.C., related to unregulated organic contaminants in Rule
62-610.568(10), F.A.C.
- Addition of cross-connection control program requirements to
Part II reuse systems that use subsurface irrigation to irrigate
residential properties.
3/9/06
The rule revisions that went into effect on March 3, 2006,
included the following:
- Creation of Rule 62-610.320(6)(g), F.A.C., to enable use of
“other” meters (like the so-called “TSS meters”) in lieu of
turbidity meters in monitoring reclaimed water. Utilities wanting to
employ the so-called “TSS meters” in lieu of turbidity meters no
longer will need to pursue a variance.
- Creation of Rule 62-610.300(4)(c), F.A.C., to clarify reporting
requirements for the annual reclaimed water scans required by Rule
62-601.300(4), F.A.C.
- Refinements to the
Annual Reuse
Report Form [adopted by reference in Rule 62-610.300(4)(a)2,
F.A.C.]. This included the addition of requirements for reporting of
plans and activities related to metering of reclaimed water use, per
statutory requirements, which were added to Section 403.064, Florida
Statutes, in 2004.
- Refinements to the
Pathogen Monitoring
Form [adopted by reference in Rule 62-610.300(4)(a)4, F.A.C.].
Requirements for use of certified labs and approved methods and for
re-testing if high pathogen concentrations are observed were added
to this form.
8/8/99
The rule revisions that went into effect on August 8, 1999,
included the following:
- Refinements to rules governing ground water recharge and
indirect potable reuse.
- Refinements to disinfection requirements for use of reclaimed
water in open cooling towers.
- Creation of a rule in Part III governing the use of various
water supplies to augment available supplies of reclaimed water.
- Creation of a rule in Part III governing aquifer storage &
recovery (ASR) of reclaimed water.
- Creation of a rule governing blending of demineralization
concentrate with reclaimed water.